The crew laying main on the Essex Ave job have completed their installation and gas on procedure and have moved to Forrest Ave between Haverford Ave and Woodbine Ave. They will be here for the next few weeks.
The crew Laying main on Woodbine Ave from Montgomery Ave to Essex Ave have installed and have gas on from Hampden Ave to Montgomery and all the services have complete for this stretch. The main on Woodbine between Essex and Hampden should be complete by the end of next week with a tentative gas on date for Friday 6/22. From here this crew will move to Grayling Ave from Woodbine to Price Ave. The crews laying on Iona Ave from Lantwyn Lane to South of Montgomery have completed their installation and gas on procedure. This crew is now laying on Meetinghouse Lane between Iona Ave and Montgomery Ave as well as Williams Ave between Meetinghouse and Woodbine. Upon the completion and gas on they will move to Wayne Ave between Essex to Narberth Ave. I may move a crew to begin laying the main on Narberth Ave late in the second week applying to this email depending on whether or not I have service crews working on Essex Ave. Barrie Rd off of Essex Ave will have a PECO crew with ULS support cameraing the existing main on or around 6/27 in preparation for the conversion now on the schedule for 7/6. The service crews are currently working Iona Ave and should have the services complete by the middle of next week. We will be moving the service crews to two jobs in Lower Merion after completing the services on Iona Ave from Lantwyn Lane to South of Montgomery Ave, Meetinghouse Lane , and Williams Ave. This may give us the potential to move on the main installation on Narberth Ave two weeks from now. Click Here for the 2018 Schedule |
AuthorNews compiled by Ed Ridgway, NBA president, marketing consultant, and a COMPASS real estate agent with the Cindy Ridgway team. Archives
May 2022
Categories
All
|